01372 360 663 info@chawtonhill.com

Croft Medical Centre, Eastergate, Hants 

Client: Primary Healthcare Properties (PHP)

Our Role: Employer’s Agent, Principal Design, Quantity Surveyor

Project Team: Contractor: Amiri Construction, Engineer: Calcinotto, Architect: Simpson Hilder

Project Details 

The Eastergate development began in 2022 with a vision to deliver a high-quality, sustainable primary healthcare facility that would achieve BREEAM Excellent standards. Our roles as employer’s agent, quantity surveyor, and principal designer involved guiding the project from inception to completion, ensuring cost certainty, compliance, and quality delivery.

Delivery and design 

The project incorporates a number of sustainability features suggested by the design and client teams. The roof is equipped with photovoltaic panels and plant. Sustainable Drainage Systems (SuDS) are included.

Challenges

We worked closely with the entire project team to overcome a number of challenges, including:

  • Cost Control – The Chawton Hill team put forward Innovative approaches to reduce additional expenditure and protect value for the client.
  • Landscaping and Bunds – We put forward solutions to manage spoil removal and bund formation, reducing costs while enhancing the site’s landscaping.
  • Power Supply – Complications with incoming power required us to closely coordinate with utility providers to resolve the issues without disrupting the project.

Outcome 

 Following a challenging start to the project, we worked with the team to deliver a high quality, BREEAM Excellent building with an EPC rating of A.

Thanks as always to the entire project team. Should you need help on cost management, design or surveying on a primary healthcare project, please don’t hesitate to get in touch with one of the team today.